Ring Road Bridge
Home/Our Work/Ring Road Bridge

Infrastructure

Ring Road Bridge

Infrastructure & Civil

Location
Koteshwor, Kathmandu
Value
₹38 Cr
Duration
14 months
Status
Completed
Ring Road Bridge 1
Ring Road Bridge 2
Ring Road Bridge 3

Overview

About This
Project

A 180-meter prestressed concrete bridge handling 40,000+ daily crossings. Completed 3 weeks ahead of schedule with full Seismic Zone IV compliance and precision formwork execution.

The Challenge

The bridge crossed an active drainage canal requiring year-round water flow maintenance during construction. Foundation conditions revealed unexpected soft strata requiring immediate geotechnical redesign mid-project.

Our Approach

A temporary diversion channel was engineered and installed before piling commenced. Deep bored pile foundations replaced the original design, and post-tensioning sequences were recalibrated for the revised load distribution.

The Outcome

Completed 3 weeks ahead of the contractual deadline. Zero structural incidents recorded. The bridge has since been cited as a reference project in the Department of Roads' infrastructure design guidelines.